Director’s new cabin – primary focus – tentative plan/dates Week 1 – concrete footings/foundation Week 2 – deck and prep for blitz Week 3 – ‘Blitz build' - walls, roof, sheeting
Week 4 - Complete details started during 'Blitz'
Week 5 - shingles, windows/doors - closed in for winter
Master Plan/Major projects Fall 08 Director’s cabin begins Clear for 4 cabin move? Spring 09 Fall 09 Director’s cabin continues Directors cabin completed Finish clearing for 4 cabin move Move 4 cabins – redo exteriors Staff outhouses? Build additional cabins? Spring 10 Fall 10 Finish 4 cabin move/exteriors Chapel clearing and footings Complete additional cabin(s)? Spring/Fall 2011 Spring 2012 Fall 2012 Chapel Chapel complete 2nd Climbing Tower begins Other possible projects on the horizon: Lodge dining room addition Replace Pavilion Property acquisition Additional cabins
|