THANK YOU to the 114 volunteers who served at Camp this Spring!
New Ropes Course – Complete phase #1 1. Build stairway to both decks – May 4-10 Dave Gutierrez design Lead carpenter: Needed plus 1-2 semiskilled
DONE
2. Install pre-fabed storage cabinets/railings – May 4-17 Dave Gutierrez design – Derrell Listhartke pre-fabbed Installer: Needed plus 1 semiskilled
TO BE COMPLETED IN THE FALL
3. Finish decking on pole platforms – May 4-17 Lead carpenter: Needed – plus 1-2 semiskilled
DONE
4. Finish metal roofing – May 11-17 - Gary Casten
DONE
Communications Tower – Phase II: May 4-10 Rick Hunt/Com Team Set up communications room in pole barn Relocate radio repeater/solar panel and cell phone system Take down old communications tower Crew needed:??
DONE
Outhouses: May 4-10 Tom Hargrove Finish the remaining details/punch list on the 3 new buildings Crew needed:??
DONE
Pavilion: May 6-11 Tom Carpino Build new deck/railings/steps Crew needs: 4-6 able to build/semi-skilled
DONE
Lumberjacks: May 7-11 Steve Brueggeman Begin clearing for director’s new cabin Crew needs: 3-4 ‘Sturdy & burley’
DONE
Older Cabin Remodeling – Complete phase III: May 14-18 Bob Rasmussen/Matt Watson Complete exteriors on Spruce/Larch/Oak/Birch – new door/upper window, deck, batons and trim. Crew needs: 4-6 able to build/semi-skilled
DONE |